Exam: SSC CGL Subject: Quantitative Aptitude Topic: Time and Work
Total Questions: 20
  1. Q1. A can complete a work in 12 days. B can complete it in 18 days. They start working together, but after 6 days, A leaves. B continues to work. After 3 more days, C joins B and they complete the remaining work in 5 days. In how many days can C alone complete the work?
  2. Q2. A clock is slow by 5 minutes every hour. If it was set correctly at 12 PM on Sunday, what time will it show at 12 PM on Monday?
  3. Q3. If a man can do a piece of work in 10 days, what part of the work can he do in 1 day?
  4. Q4. A and B can complete a work in 10 days and 15 days respectively. They start working together, but after 2 days, B leaves. A continues to work alone for the next 3 days. After that, C joins and completes the remaining work in 5 days. In how many days would C alone have completed the work if he had started on the same day as A and B?
  5. Q5. The average of 10 numbers is 15. If each number is increased by 5, what will be the new average?
  6. Q6. The ratio of the ages of a father and son is 10:3. The difference between their ages is 28 years. What is the age of the son?
  7. Q7. A merchant sells his goods at a profit of 20%. He also uses a weight of 900 grams instead of 1 kg. What is his overall profit percentage?
  8. Q8. A can complete a work in 10 days. B can complete the same work in 15 days. In how many days can they complete the work together?
  9. Q9. What is the probability of getting a sum of 7 when two fair dice are rolled?
  10. Q10. A cistern can be filled by pipe A in 4 hours and emptied by pipe B in 6 hours. If both pipes are opened, how long will it take to fill the cistern?
  11. Q11. A is twice as good a workman as B and hence finishes a job in 30 days less than B. How many days will both take to finish the job together?
  12. Q12. If 3 men can do a work in 10 days, how many days will 5 men take to do the same work?
  13. Q13. A worker earns Rs. 500 for a 10-hour workday. If he works overtime for 2 hours at double the rate, what is his total earning for that day?
  14. Q14. P completes 1/7 of a job daily. How long will it take P to finish the job?
  15. Q15. Two pipes A and B can fill a tank in 30 minutes and 45 minutes respectively. A third pipe C can empty it in 60 minutes. If all three pipes are opened, in how much time will the tank be filled?
  16. Q16. A sum of money is divided between P and Q in the ratio 4:5. If P gets Rs. 300 more than Q, find the total sum.
  17. Q17. If the current year is a leap year, how many days are in February?
  18. Q18. A takes 20 days to complete a work, and B takes 30 days to complete the same work. How long will it take for both of them to complete the work together?
  19. Q19. Worker A, B, and C can complete a job in 12, 15, and 20 days respectively. They start together, but C leaves after 4 days. How many days will A and B take to complete the remaining work?
  20. Q20. The age of a father is 5 times the age of his son. 5 years ago, the father was 7 times as old as his son. What is the present age of the father?

Seamless prep with the tools you already use.

Study across devices, save bookmarks, get smart reminders, and track progress—so your mock tests and AI plans stay in sync.

Elevate your prep today

Streamline practice, track weak topics, and improve faster with AI-guided revision. Try Meltwish free.